When Should You Commission a Ferro Scan? The Concrete Works Scenarios That Make It Non-Negotiable
November 16, 2026 3:27 pmOn most fit-out and refurbishment jobs there comes a point where someone glances at the programme, then at the budget, and asks whether the scan is really needed. It’s a fair question. Quite often, though, the answer is a firm yes, and finding that out the hard way costs far more than the scan ever would.
So how do you decide? Working out when to commission a ferro scan comes down to one simple test. If drilling or cutting in the wrong spot could hurt someone, weaken the structure, hit a live service or bring the job to a halt while engineers work out what to do next, you scan first. In our experience that covers a lot more work than people expect.
Our ferro scanning page explains how the survey itself works, so here we’ll stick to the situations where it really isn’t optional.
When to commission a ferro scan, and when you can skip it
There are a few jobs where you could reasonably go without. A handful of shallow fixings into a non-structural screed, say, or a light fitting into a block wall you know isn’t load bearing. We’d still suggest a quick check, but the stakes are low.
Everything else depends on what’s at risk if you hit something. Reinforcement isn’t just steel getting in the way of your drill; it’s what’s holding the slab up. Tendons in a post-tensioned slab are under enormous load. Conduits cast into the concrete might well be live. Look at it that way and the line gets much clearer.
The scenarios below are the ones we see again and again, and each of them makes a scan non-negotiable.
Core drilling for water mains, HVAC and electrical containment
This is the one we’re asked about most, and it’s easy to see why. Services have to get through slabs and walls somewhere, and the cores tend to be large and plentiful.
A diamond core doesn’t stop politely when it meets a bar. It goes straight through. Clip one secondary bar and the engineer might just shrug. Cut through a cluster of main bars near a column, or into a beam nobody knew was there, and you’ve got a structural problem that has to be assessed before anyone carries on. Meanwhile the M&E programme sits waiting.
It isn’t only steel, either. Electrical conduit, heating pipes and old services all turn up inside slabs, and some are live. Scanning early means core positions can be shifted to clear the steel before the design is fixed, which is far cheaper than rerouting a duct after the holes are already in.
Cutting openings in concrete floors or walls
New stair voids, lift shafts, risers and doorways all mean cutting through a lot of reinforcement at once. Some loss of steel is often expected and designed for. The trouble starts when nobody knows where the bars are, how many there are, or whether there’s a beam or a band of heavy reinforcement right where the opening is going.
Without a scan, the structural engineer is designing around guesswork. With one, they can position the opening to avoid the critical steel, or at least design the trimming and strengthening properly. That’s the difference between a planned modification and a frantic scramble.
Why is cutting a post-tensioned tendon so dangerous?
This is the one we feel most strongly about. Post-tensioned slabs rely on steel tendons stressed to very high loads, which is how they manage such long spans with such slim sections. That stored energy doesn’t go anywhere while the tendon sits quietly in its duct.
Cut one, particularly an unbonded tendon, and the energy can release suddenly and violently. Tendons have been known to burst out through slab edges. Even if nobody’s hurt, the damage is serious, because the slab loses capacity over a wide area rather than just around the hole. Repairs are specialist, slow and expensive.
So with PT slabs it’s simple. Always scan, every time. Tendons drape through the slab (low at midspan, high over the supports), so you can’t assume a safe zone from a drawing.
One quick note: tendons in plastic ducts can sit deeper or be harder to detect, which is where GPR often comes in alongside ferro scanning, and we cover that in a separate article.
Do you need a scan before fixing anchors into concrete ceilings?
Usually, yes. Overhead anchors for services, ceiling grids, plant supports and containment go in by the hundred, and the bottom reinforcement sits close to the soffit, right where the drill bit enters.
Hit a bar overhead and you’ll normally abandon the hole and drill another nearby, which can leave the fixing short of its edge or spacing distances. Do that across a whole floor and the delays add up quickly. On a PT slab, those same soffit fixings come uncomfortably close to tendons, so everything above applies with even more force.
What are the risks of fixing near existing rebar?
Anchor manufacturers work out design capacities for specific conditions, and a bar running through the fixing zone isn’t one of them. Drill into a bar and you’ll either abandon the hole, damage the bar or end up with an anchor installed in less than ideal conditions. Any of those can reduce capacity, and fixings for structural steel, balustrades or heavy plant don’t have much margin to spare.
Scanning first lets the designer place fixings with confidence, adjust a baseplate if needed and avoid failed pull out tests later on. That’s a much better use of everyone’s afternoon.
What happens when the scan gets skipped?
We won’t name names, but these stories follow a depressingly familiar pattern. Picture a few of them.
A fit-out contractor racing towards handover decides the as-built drawings are good enough and cores a run of holes for a new drainage route. One core goes straight through a group of bars beside a column. Work stops, the structural engineer gets called back and the route is redesigned. The scan would have taken a day; the delay takes weeks.
Or a team putting anchors into a car park soffit starts drilling without checking whether the slab is post-tensioned. Nobody’s injured, which is pure luck, but a tendon is damaged and the whole bay is closed while specialists assess and repair it.
Or an M&E coordinator inherits a building where the structural drawings show a lovely neat bar layout. On site, the bars look nothing like it, and half the planned penetrations clash.
Wait, the drawings were wrong? Not quite. They just showed what was designed, not what was built.
None of these are unusual… and that’s exactly the point.
Don’t as-built drawings cover it?
Sadly not. As-built drawings are useful, but they record intent rather than reality. Bars shift during the pour, spacing drifts, extra steel goes in around openings, and later alterations often never make it onto paper at all. On older buildings, the drawings may be missing or simply wrong.
Use the drawings as a starting point and the scan as the check.
Getting the timing right
Knowing when to commission a ferro scan is partly about the work and partly about the programme. The sweet spot is once the area is accessible and before penetration and fixing positions are frozen. That’s usually just after strip-out, when the finishes are off, but early enough for the results to feed into M&E coordination and structural design.
Scanning the day before the drilling crew turns up is better than nothing. It does leave you no room to move anything if there’s a clash, though, and that’s frustrating for everyone.
The things that really shape timing are the programme, access, the number of penetrations and whether the slab might be post-tensioned. On site preparation, the surface needs to be clear and reasonably clean, and we’ll confirm the details when we book you in.
Why it’s worth it
Commissioning a ferro scan before structural modifications isn’t about ticking a box. It turns an unknown into something you can design around. You get fewer abandoned holes, fewer nasty surprises and no tendon incidents, and nobody has to make that awkward call to the structural engineer halfway through the programme.
We’ve found it’s a real boost to everyone’s confidence on site, and usually to the budget as well.
Frequently asked questions
Can a ferro scan be part of a building survey package?
Yes, and it often makes sense. If you’re already commissioning a measured survey, utility survey or other site investigation, adding ferro scanning to the same visit saves on mobilisation and gives you one joined up set of information. Castle Surveys delivers all of this in-house, so combining them is straightforward.
Who is responsible for arranging a concrete scan before drilling?
That depends on your contract, so it’s worth checking. In practice, whoever is carrying out the drilling or cutting usually arranges it, while designers and principal contractors are expected to identify the risk and make sure it’s planned for under CDM. What matters is that somebody owns it before the drill comes out.
Do I still need a scan if I have as-built drawings?
Yes. Drawings show what was designed, not necessarily what was built, and they rarely pick up later alterations. Plan with them, then scan to confirm.
Before the drill comes out
Planning core drilling, openings or fixings into concrete and not sure whether you need a scan? Ask us. We’ll give you a straight answer, and if it genuinely isn’t needed, we’ll tell you