Setting Out Tolerances in Construction: Which Standards Apply and How Compliance Is Verified
November 16, 2026 3:19 pmTolerances are one of those things everybody signs up to and hardly anybody reads properly. They sit quietly in the specification, often just a line or two, until a column comes up out of plumb, a cladding bracket refuses to line up, or two parties start arguing about whose fault it is.
Our setting out team works to published and contract-specific tolerances every single day, and two problems crop up far more often than they should. Some specifications say nothing useful about tolerances at all, which leaves plenty of room for a dispute later on. Others ask for something so tight that the construction method can’t possibly deliver it. Neither is much fun once the work’s in the ground.
So what do construction setting out accuracy standards actually ask for when it comes to setting out tolerances in construction? And how do you prove you’ve met them? Let’s work through it.
Is BS 5606 still relevant?
Here’s one that catches a lot of people out. Plenty of specifications still quote BS 5606:1990, but that edition was replaced in February 2022 by BS 5606:2022, Accuracy and tolerance in design and construction. Guide. If your documents still cite the 1990 version, they’re pointing at a superseded edition.
It helps to be clear about what BS 5606 actually is, too. It’s a guide rather than a specification, so you won’t find a tidy table of pass or fail values in it. What it gives you is a way of thinking about accuracy and tolerance across the whole project. That covers deciding what dimensional performance the design really needs, judging whether a tolerance is achievable, and checking the work through surveys before, during and after construction. The 2022 edition also separates accuracy (how close a measurement or position is to the true value) from tolerance (how much deviation you’re allowed) far more clearly than the old one did.
There’s one detail that’s worth knowing. The 2022 edition keeps the old BRE industry performance data from the 1970s and 1980s in Annex C, but purely for reference, and it says plainly that those figures shouldn’t be used to judge current practice. If someone waves those historic tables at you as a target, treat it as a warning sign.
So yes, it’s still very relevant. BS 5606 tolerances aren’t numbers you build to; the standard is the framework that helps you pick sensible numbers in the first place.
Where the Eurocode execution standards come in
This is where most of the hard numbers live.
For concrete, it’s BS EN 13670 Execution of concrete structures, which sets out its geometrical tolerances in Section 10.
For structural steel, it’s BS EN 1090-2. Its tolerances sit in Annex B and come in three flavours: essential tolerances (which matter for strength and stability), functional tolerances (for fit-up and appearance) and any special tolerances a project decides to specify. The steelwork erection tolerances are in Tables B.15 to B.25.
In the UK, these usually reach a contract through the national specifications. The National Structural Concrete Specification (NSCS), now in its 5th edition after launching in July 2025, works alongside BS EN 13670. The National Structural Steelwork Specification (NSSS), currently the 7th edition with its 2023 revision, does the same job for BS EN 1090-2.
Here’s how the main documents fit together:
| Standard or document | What it covers | How it applies on site |
| BS 5606:2022 | Guidance on accuracy and tolerance across design, construction and verification | Helps set a realistic tolerance strategy and plan how compliance will be checked; not a pass or fail specification |
| BS EN 13670 + NSCS | Execution of concrete structures, including geometrical tolerances in Section 10 | Sets the tolerances for in situ concrete elements when the specification calls them up |
| BS EN 1090-2 + NSSS | Execution of steel structures, with essential and functional tolerances in Annex B | Sets fabrication and erection tolerances for steelwork, with erection values in Tables B.15 to B.25 |
| Contract or contractor specification | Project-specific requirements, which may adopt, tighten or relax the standards | Usually the document you’re actually checked against, so it needs to be clear and achievable |
What are the standard setting out tolerances for reinforced concrete frames?
It’s a question we hear a lot, and the honest answer is that it depends on what your specification calls up.
On most UK concrete frames, that’ll be the Section 10 tolerances in BS EN 13670, brought in through the NSCS. Tolerance class 1 is the normal default, while class 2 is a tighter option that has to be asked for specifically.
We won’t reproduce the individual values here. They should always be read from the current edition, in context, alongside any project amendments. The thing that matters most is that your specification says which standard and which class applies, so everyone’s measuring against the same yardstick.
How do contractor specifications deal with tolerances?
In our experience, they’re all over the place. The good ones name the standard, the edition and the class, and explain where project-specific tolerances differ and why. The less good ones copy a clause from the last job, quote a withdrawn edition or simply say “within normal tolerances”. Normal according to whom, exactly?
What if the specification is silent?
Silence doesn’t mean there’s no tolerance. It means nobody has agreed one, which is worse.
The moment something doesn’t fit, each party reaches for whichever reference suits them, and suddenly everyone’s arguing about which standard should have applied instead of sorting the problem out. It’s frustrating, it’s slow and it’s completely avoidable.
If you spot a silent specification, flag it early. A quick clarification at tender stage saves an awful lot of grief later.
And what if the tolerances are unrealistically tight?
This happens just as often. A designer specifies something that’s perfectly achievable in a factory, then applies it to in situ concrete poured on an exposed site in the middle of February.
Wait, didn’t anyone check the method could achieve it? Quite often, no.
Tight tolerances aren’t wrong in themselves. Some interfaces really do need them, particularly where precast units, curtain walling or lift guide rails meet the frame. The trouble starts when tightness is applied across the board without anyone asking whether it’s necessary, or even possible. That’s exactly the judgement BS 5606:2022 is there to support, by looking at achievability before a tolerance is fixed rather than after.
Standard or specification: which wins?
Generally, the contract does. A British or European standard only binds a project when the contract calls it up, and the specification can adopt it as written, tighten it or relax it. Where documents conflict, the contract’s order of precedence decides.
We’re surveyors rather than lawyers, so if there’s real doubt it’s worth taking advice. The practical lesson still holds, though: read what’s actually been specified rather than assuming the standard applies untouched.
What gets checked on site, and when?
Verification follows the build.
- Control and grid lines are checked before anything is set out from them.
- Formwork, holding-down bolts and cast-in items get checked before the concrete goes in (once it’s poured, it’s far too late).
- Columns, walls and slab edges are surveyed after striking.
- Steelwork is checked once it’s erected and before baseplates are grouted and connections finalised.
- Interfaces such as cladding brackets and lift shafts are checked before the next trade relies on them.
Timing matters every bit as much as accuracy. A check that turns up after the follow-on trade has started isn’t really verification; it’s archaeology.
Our construction verification surveys are built around catching problems while they’re still cheap to fix, and our site engineering and setting out work (robotic layout with HP SitePrint included) is about getting things right before there’s anything to verify.
What should a setting out sign-off record include?
A sign-off record has to stand up months down the line, when the people who did the work may well have moved on. At the very least, we’d expect to see:
- The element and its location, referenced to the project grid.
- The design value, the measured value and the deviation between them.
- The tolerance applied and where it came from (standard, edition, clause and class, or the relevant specification clause).
- The control used and the instrument, with its calibration status.
- The date, the surveyor and whoever accepted the work.
- And a clear pass or fail, with any non-conformance and the agreed action written down.
If a record can’t tell you which tolerance was applied and why, it isn’t much of a record.
Who’s responsible when work falls outside tolerance?
That depends on why it happened and what the contract says. If the setting out was wrong, the setting out party will usually carry it. If the setting out was right and the element moved during construction, it may sit with the trade contractor. And if the tolerance was never achievable to begin with, the question may well end up back with the designer.
Clear specifications and good records are what turn that blame game into a simple check.
Frequently asked questions
What happens if the specification doesn’t state tolerances?
There’s no agreed target, so disagreements become far more likely. Raise it early and agree which standard, edition and class apply before work starts. It takes minutes and can save weeks.
What happens if work is built outside tolerance?
It should be recorded as a non-conformance and assessed. Sometimes the deviation is acceptable with the designer’s agreement; sometimes the element has to be corrected or the follow-on work adjusted. The sooner it’s caught, the cheaper the fix.
Who is responsible for checking setting out on site?
Usually the contractor, through its own site engineers or a specialist setting out team, with independent checks often required by the client or principal contractor. The specification should spell this out, including who signs off and when.
Getting tolerances right from day one
Tolerances only work when they’re clear, achievable and checked at the right moment. Get those three right and most disputes never happen. We’ve found that ten minutes talking about tolerances at the start of a job is worth far more than ten hours arguing about them at the end.
If you’re reviewing a specification, or you’d like an independent check on work that’s already under way, have a chat with our team. We’ll give you a straight view on what’s realistic and how compliance can be shown.
Comments are closed here.